Allocation Round 8 (AR8) of the UK's Contracts for Difference (CfD) scheme is the first round in which the government has formally declined to set a meaningful budget before it sees what developers are prepared to bid. On 19 November 2026, the Department for Energy Security and Net Zero (DESNZ) published its Contract Budget Notice with notional initial budgets of £1 for each of Pots 1–4 — including fixed-bottom offshore wind in Pot 3 and floating and Other Deepwater Offshore Wind (ODOW) in Pot 4 — while confirming a final £0 for Pot 5, the emerging-technologies pot that covers tidal stream and wave.
For suppliers, developers and investors, the immediate message is that AR8's outcome, and therefore any steel or fabrication demand it might eventually generate, is unresolved. The auction is not a construction project; it is a procurement process whose output is a set of contracts with individual projects. No developer, EPC contractor or steel supplier can be tied to AR8 at this stage.
What the £1 actually means
A £1 budget cannot clear a single project. It is a placeholder, not a policy decision against offshore wind. DESNZ intends to review anonymised bid stacks across all four pots in early 2027 — the first round with that visibility spanning solar and onshore wind as well as fixed-bottom and floating offshore wind — and will then publish final budgets, which may be raised if the bid prices are judged to be in consumers' interest. HM Treasury is involved in those decisions.
The UK government framed the round around affordability and "strategic technologies capable of delivering clean power at scale in the near term". This echoes the pattern of recent rounds: budgets have been revised late in the process, and the price-clearing competition has done most of the work in determining capacity.
The structure of the round itself is set. Administrative Strike Prices, in 2024 money, were held at AR7 levels:
| Pot | Technologies | ASP (£/MWh, 2024 prices) |
|---|---|---|
| Pot 1 | Solar PV (>5 MW) | 75 |
| Pot 2 | Onshore wind, remote island wind (>5 MW) | 92 |
| Pot 3 | Fixed-bottom offshore wind | 113 |
| Pot 4 | Floating offshore wind and Other Deepwater Offshore Wind | 271 |
| Pot 5 | Emerging technologies (tidal stream, wave) | £0 budget, final |
Separate clearing-price groups for Scotland and the rest of Great Britain remain, recognising cost differentials. No minima, maxima or capacity caps apply to any pot.
Pot 5 is the clearest casualty. Because emerging-technology bids are not visible in the same way as the larger pots, its £0 budget is final — meaning no tidal or wave project can win a contract in AR8. That removes one potential, if limited, source of steel demand for marine-energy structures.
A new category with real steel implications
AR8 introduces a dedicated classification for Other Deepwater Offshore Wind, following DESNZ's July 2026 government response confirming majority support for the change. ODOW is intended to remove barriers to CfD support for novel deepwater foundation concepts — the designs that fall between conventional fixed-bottom monopiles and fully floating platforms.
This is where AR8 is most technically interesting for the metals supply chain. Fixed-bottom offshore wind is dominated by monopiles and jackets, and towers are a mature, well-supplied market. Floating wind currently leans heavily on semi-submersible and spar designs, with significant steel-intensive fabrication. ODOW creates a route for hybrid and deepwater concepts — potentially gravity-based, compliant or articulated structures, or large jackets in deeper water — to compete for support at the same £271/MWh strike price as floating wind.
The category is new and its eventual project pipeline is unknown, so this is an area to watch rather than a procurement opportunity in the near term.
Precedent cuts both ways
AR7, whose results were confirmed on 14 January 2026, awarded 8,437.5 MW across 12 projects, of which about 8.2 GW was fixed-bottom offshore wind. Six fixed-bottom projects cleared at a capacity-weighted average of roughly £90.91/MWh, with the main clearing price at £65.45/MWh in 2012 prices. RWE alone took CfDs covering about 6.9 GW, including Norfolk Vanguard and the two Dogger Bank South projects.
That outcome shows what a well-funded round can do. But it also sets the bar: developers now have relatively recent, clearly priced contracts to benchmark against, while AR8 offers them a placeholder budget. If the final budget comes in low, even a well-structured round could deliver little new capacity — and that, rather than the £1 headline, is the real uncertainty.
Where the steel question actually sits
The procurement status of AR8 is not a steel question at all. Nothing has been tendered, awarded or delivered under this round; the procurement assessment lists steel structures for monopiles, jackets and towers as unverified. Whatever steel demand AR8 eventually creates will be decided by winning developers' own project-level final investment decisions and their tier-one fabrication contracts — decisions that fall years after the round concludes.
There is one thread worth flagging: the Clean Industry Bonus (CIB). AR8's CIB framework sets a final budget of £515 million, with a portion ring-fenced for floating offshore wind, and requires successful bidders to meet minimum supply-chain investment standards — £100 million per GW for fixed-bottom offshore wind and £50 million per GW for floating. Eligible investment categories explicitly include facilities manufacturing, assembling or installing blades, nacelles, towers and foundations, including transition pieces and secondary structures.
The CIB is not a steel procurement opportunity in its own right, but it is a direct lever on where future UK fabrication capacity for towers and foundations is built. AR8's CIB outcomes — not its strike prices — are probably the most steel-relevant thing about the round, and even those depend on which projects actually win.
What to watch
- Early 2027: DESNZ review of anonymised bids across Pots 1–4, followed by final budget publication.
- 15–17 February 2027 (scheduled): AR8 results announcement.
- Thereafter: CfD signature, individual project FIDs and the fabrication and steel orders that follow them.
AR8's real significance is procedural: the UK has moved to a bid-first budgeting model in which the government sets the money after seeing the market's offer. Whether that produces better value or simply delays investment is the debate to have. For the steel supply chain, the round is a signal about future demand — nothing more, and not yet.