Key facts at a glance
| Item | Detail |
|---|---|
| Capacity / configuration | 315 MW; 21 × Vestas V236-15.0 MW |
| Location | Off Oga, Katagami and Akita cities, Akita Prefecture, Japan |
| Owners | Oga Katagami Akita Offshore Green Energy LLC: JERA Nex bp, J-POWER, Tohoku Electric Power, ITOCHU |
| Selected as business operator | 13 December 2023 (METI / MLIT, Sea Area Utilization Act) |
| Target COD | 30 June 2028 |
| Offshore installation | Foundations from spring 2027 (Kajima); turbines H2 2027 (Sea Challenger via Japan Offshore Marine) |
| Construction base port | Akita Port |
The Oga–Katagami–Akita offshore wind farm is not the largest project in Japan's pipeline, nor the most novel in technology. Its significance is structural: it is the first project selected under Japan's Round 1 auction regime that appears genuinely on track to reach commercial operation, and its supply chain decisions are being watched as a template for everything that follows.
Where the project actually stands
The project company has begun moving physical components to Akita Port. The first batch of monopile foundations was delivered in September 2026, followed by the first turbine towers in late October/November 2026. These are staging moves, not offshore installation. Offshore foundation work is planned from spring 2027, with turbine installation in the second half of 2027 aboard the jack-up vessel Sea Challenger.
That sequencing matters commercially. Almost all of the heavy steel and marine installation capacity for this project is already contracted. The forward-looking packages that remain are mostly interface management, port logistics, commissioning and the start of a long O&M phase — not new major supply opportunities.
The steel story: a genuine first, but narrower than it looks
The headline steel fact is real and consequential. JFE Engineering has manufactured Japan's first domestically produced offshore wind monopiles at its Kasaoka Monopile Factory in Okayama Prefecture — a facility purpose-built for this market, with roughly 80,000–100,000 tonnes per year of capacity and the ability to handle monopiles up to about 12 m in diameter and 2,500 t in weight. JFE received the monopile manufacturing and transportation order from Kajima in December 2025; Kajima itself had signed the foundation contract with the project company in October 2025, covering manufacturing, procurement, transport and installation.
For the Japanese steel sector, this is the first tangible evidence that the domestic supply chain can absorb heavy-gauge plate into finished offshore foundations, rather than simply exporting plate or importing finished monopiles. JFE's use of its own heavy plate and its Tsu Works for transition-piece completion keeps a meaningful share of the steel value chain onshore.
But the boundary of that achievement deserves emphasis. Domestication here covers the monopile, not the full foundation steel package, and not the towers. Vestas' public documentation for the turbine package cites a planned domestic procurement ratio of around 38% for the wind turbines — a figure that includes blades, nacelles and towers. The tower manufacturer has not been publicly disclosed in the sources reviewed, and the origin of tower steel is unresolved. Readers should treat the "domestic monopiles" milestone as a genuine first in one component, not as evidence that the project's structural steel is broadly local.
Ownership and contracting: who is actually doing what
The project company, Oga Katagami Akita Offshore Green Energy LLC, was established in February 2024 following the December 2023 selection of the JERA-led consortium by METI and MLIT. Its members are JERA Nex bp, J-POWER, Tohoku Electric Power and ITOCHU — a combination that pairs Japan's largest thermal/transition utility, a major wholesaler, a regional utility with grid interests in the area, and a trading house with local commercial reach.
The contracting structure around foundations and installation has been misreported in some coverage, and the distinction matters commercially:
- Kajima Corporation holds the foundation contract (manufacturing, procurement, transportation and installation) signed in October 2025. This is the construction-side award.
- JFE Engineering holds the monopile manufacturing and transportation subcontract from Kajima (December 2025).
- Japan Offshore Marine (JOM) — a joint venture of DEME Offshore (49%) and Penta-Ocean Construction (51%) — won the turbine installation contract on 29 May 2026, covering engineering and vessel charter, with Sea Challenger to be upgraded and reflagged Japanese. Reported value is up to roughly €50 million.
- JFE Engineering and Akita Maritime Service formed a joint venture that, in November 2026, won a five-year long-term periodic inspection and maintenance contract for balance-of-plant assets: the onshore substation, onshore transmission line, subsea cables and monopile foundations.
That last point has been widely garbled. The JFE/Akita Maritime Service award is an O&M contract, not a construction BOP award. The tender documents and JFE's own release describe periodic inspection and maintenance over an initial five-year term, extendable across the project life, and JFE presents it as a domestic first for a Round 1 auction project. Readers who saw the November 2026 coverage described as a "BOP construction contract" should correct that impression: the construction-side BOP scope is not established in the public record as awarded to this JV.
Why the O&M award matters more than it appears
The five-year O&M award is arguably the most strategically interesting development in the project's recent history, because it begins to define what a Japanese offshore wind O&M industry looks like in practice.
The project company has stated an ambition to build "Japan's largest offshore O&M company" with 86% of employees drawn from Akita — a corporate target rather than a verified outcome, but a signal of intent. Akita Maritime Service's role in the JV — handling onshore transmission-line inspections and arranging workboats and guard vessels — fits that local-employment model. Pairing it with JFE Engineering, which now spans monopile manufacturing, transition pieces and long-term inspection, gives the project a vertically integrated domestic maintenance capability that few other Japanese projects can yet claim.
For steel-industry readers, the long-term inspection scope over monopile structures is a reminder that foundation steel has a multi-decade service obligation. Weld inspection, corrosion protection and structural monitoring over the 2028–2050+ operating horizon will be recurring, technically demanding work. That is not an opportunity created by this project alone, but this project is where Japan first builds the institutional experience.
Timeline of principal milestones
| Date | Milestone |
|---|---|
| Dec 2023 | Consortium selected as business operator (METI/MLIT) |
| Feb 2024 | Project company established |
| Apr 2024 | Kasaoka Monopile Factory begins operations |
| Dec 2024 | Vestas firm order for 21 × V236-15.0 MW |
| Oct 2025 | Kajima foundation contract signed |
| Dec 2025 | JFE Engineering monopile order from Kajima |
| May 2026 | JOM (DEME/Penta-Ocean) turbine installation award |
| Sep 2026 | First domestic monopiles delivered |
| Nov 2026 | First turbine towers arrive at Akita Port; JFE/Akita Maritime O&M contract |
| Spring 2027 | Offshore foundation installation planned |
| H2 2027 | Turbine installation planned (Sea Challenger) |
| 30 Jun 2028 | Target commercial operation date |
The real test ahead
The project's credibility now rests on execution rather than contracting. Three risks stand out:
Weather and vessel availability. Akita's offshore waters see demanding winter conditions. The sequence — foundations in spring 2027, turbines in H2 2027 — leaves little buffer before the June 2028 COD. Sea Challenger is a single, critical asset; a reflagging, upgrade or schedule slip would cascade directly onto the COD target.
Localisation credibility. The 38% turbine domestic procurement figure is a plan, not a delivered outcome. If towers arrive from overseas suppliers, the project's localisation story weakens considerably, and the Round 2/3 projects that follow will face harder questions from METI about domestic content.
Supply-chain depth. Japan has exactly one monopile factory. The Kasaoka line is now serving this project, but the country's Round 2 and Round 3 pipelines will require multiples of this capacity. Whether JFE expands, whether competitors enter, and whether Japanese steelmakers can sustain heavy-plate supply at the required thickness and quality, are questions this project will begin to answer through its own delivery performance.
What to watch
Investors and suppliers should focus on four observable signals: (1) confirmation of monopile installation start and pace in spring 2027; (2) disclosure of the tower manufacturer and its steel origin; (3) the terms and scope of any remaining construction-side BOP awards; and (4) commissioning milestones in late 2027 that test the June 2028 COD date.
For the steel sector specifically, the project's legacy is likely to be less about tonnage — modest at 21 monopiles and 21 towers — than about whether Japan has finally established a bankable domestic foundation supply chain. That answer is now being assembled, one monopile at a time, at Kasaoka.