Rosatom's engineering arm has finished manufacturing the reactor internals and the VVER-1200 reactor head for El Dabaa Unit 1, completing the full reactor set for Egypt's first nuclear unit. The parts were made at the Izhora site near St Petersburg and, together with the reactor pressure vessel already installed on site in November 2025, total more than 670 tonnes; about 340 tonnes of internals and head now await shipment to Egypt.

The milestone is real but narrow. It closes the primary-circuit fabrication package for the reactor proper. It does not close the reactor hall, and it does not open a meaningful new procurement window for outside suppliers.

What was actually completed

The internals comprise the shaft, baffle and protective tube block; with the head, they fix fuel placement and provide the reactor's leak-tightness and core support. Rosatom frames completion as the point at which site workers can move on to "installation of the remaining reactor hall equipment and move forward with commissioning."

That phrasing is the important qualifier. Steam generators, main coolant pumps, the pressuriser and main coolant pipeline are still being installed. Egyptian state media reported the start of first steam generator installation at Unit 1 in October 2026 — a full year after the vessel went in. In other words, the reactor set is complete in the factory, but the reactor hall is not complete on site.

Where the steel actually comes from

The most useful thing this announcement reveals is the degree to which the VVER-1200 heavy-equipment supply chain is vertically integrated inside Rosatom's Mechanical Engineering Division. There is no open mill or forgemaster market here.

StageEntityLocationRole
Steelmaking, forging, pressing, heat treatment, rough machiningAEM-Special Steels (AEM-Spetsstal)Izhora industrial site, St PetersburgMetallurgical blanks for RPV, pressuriser, main coolant pipeline
Welding, assembly, final machiningIzhora Plants (AEM-Technologies)Kolpino, St PetersburgReactor vessel, internals, head
Steam generators, pressuriser, Unit 2 vesselAtommashVolgodonskHeavy reactor equipment
Pump casings, MCP pipe assemblies, valvesPetrozavodskmashPetrozavodskPrimary circuit components

For Unit 1 specifically, AEM-Special Steels shipped 24 large metallurgical blanks totalling more than 650 tonnes in July 2024, covering the reactor vessel, pressuriser and main coolant pipeline. Egypt's regulator, ENRRA, inspected the AEM Special Steels branch in April 2022 under its quality-assurance programme for Unit 1 pressure-vessel blanks — an unusual and notable detail, since it means the Egyptian regulator has visibility into the steelmaking stage itself, not just the finished component.

Note the plant attribution that circulates in some commentary: the Unit 1 vessel was built at Izhora, not Atommash. Atommash built the Unit 2 vessel and the steam generators and pressuriser shipped to El Dabaa in mid-2026.

Procurement: what is closed and what is not

The primary heavy-equipment packages for Unit 1 are substantially placed and, in the case of the reactor, largely delivered. The procurement that remains live at El Dabaa is not steel-intensive in the way the reactor set was.

  • Closed / delivered: reactor pressure vessel (installed November 2025), reactor internals and head (manufactured, awaiting shipment), steam generators and pressuriser for Unit 1 (shipped 2026, installation under way).
  • Not evidence of an open package: the framing of "remaining reactor hall equipment" should not be read as a tender opportunity. These components are already contracted to Rosatom's machine-building plants and are in manufacture or transit.
  • Turbine island: contracted to Korea Hydro & Nuclear Power under an August 2022 agreement with Atomstroyexport covering turbine-island buildings, structures, equipment and materials for all four units. That package is placed, not open.
  • Speculative at best: local-content manufacturing. Egypt's Ministry of Electricity and the Arab Organization for Industrialization have discussed localising electrical systems, equipment and tooling, and the World Nuclear Association has cited local content for Unit 1 at roughly 20%, rising for later units. No public evidence shows a steel-related award to an Egyptian fabricator for Unit 1's nuclear island. Treat any local-content opportunity as a medium-term, units 2–4 story rather than a Unit 1 one.

Schedule: the milestone is early relative to commissioning

The completion of reactor manufacture in late 2026 sits comfortably ahead of the published commissioning timeline, which is worth stating plainly because it corrects an easy misreading.

MilestoneDate
Construction permit (ENRRA)29 June 2022
First safety-related concrete20 July 2022
RPV delivered to site21 October 2025
RPV installed19 November 2025
First steam generator installation beginsOctober 2026
Reactor internals and head manufacturedNovember 2026
Pre-commissioning tests scheduledQ4 2027
Commissioning targetedQ4 2028

Egypt's Nuclear Power Plants Authority published the Q4 2027 / Q4 2028 dates, consistent with the Prime Minister's July 2025 statement that Unit 1 would start operations in the second half of 2028. Fuel delivery is being prepared for 2027. The gap between "reactor manufactured" and "fuel load" is therefore roughly two years — normal for a large PWR build, and a reminder that fabrication milestones are not commissioning milestones.

Why it matters beyond one unit

El Dabaa is a four-unit, 4,800 MW programme under an EPC package agreed in 2016 and effective from December 2017, with Rosatom's Atomstroyexport as general contractor and Atomenergoproekt as designer. Unit 1's reactor set finishing on schedule is the clearest signal yet that the Izhora–Atommash–Petrozavodskmash chain can hold cadence across four units: Unit 2's vessel is in production, Unit 3 pressuriser and pump work is under way, and Unit 4's reactor vessel steel was cast in 2025.

For Egypt, the sequence matters commercially as much as technically. The country is building its first nuclear plant with roughly 80% imported content on Unit 1; the credibility of the localisation pitch for later units depends on Units 1 and 2 entering commissioning on the published dates. For the steel sector, the takeaway is structural rather than transactional: a nuclear new-build programme of this scale consumes several thousand tonnes of specialty forgings per unit, and in this project essentially all of that flows through one vertically integrated Russian supplier. The commercial opening, where one exists, is in balance-of-plant steel, conventional island materials and, over time, Egyptian fabrication content — not in the nuclear island.