Amplitude Energy (formerly Cooper Energy) has crossed two thresholds that matter more than any single well result: the East Coast Supply Project (ECSP) took final investment decision on 30 September 2026, and the Annie-2 development well has now been drilled, cleaned up and suspended for future completion. Together they convert a long-running Otway Basin concept into an execution-phase project with a disclosed cost envelope and a 2028 first-gas target.

The most useful new information is the reservoir read-through. Preliminary Annie-2 data point to better permeability, porosity and deliverability than the original 2019 Annie-1 discovery, according to trade reporting of the well result. That is a positive signal for well productivity in the Waarre C, but it is early: the well has not been produced, and no revised resource estimate has been published.

What ECSP actually is

ECSP is not a new platform development. It is a subsea tie-back campaign in the offshore Otway Basin, Victoria, designed to bolt incremental gas wells into Amplitude's existing Casino–Henry–Netherby (CHN) subsea pipeline, which lands at the Athena Gas Plant near Port Campbell. The regulatory architecture confirms the concept: NOPSEMA accepted the project's Offshore Project Proposal on 7 July 2025, covering "up to 8 incremental gas development opportunities with associated wells, flowlines and manifolds."

The OPP lists confirmed resources at Annie and Henry, with prospective resources at Elanora, Heera, Juliet, Nestor, Isabella and Pecten East across titles VIC/L24, VIC/P76, VIC/L37 and VIC/PL37. Titleholder of record remains Cooper Energy (CH) Pty Ltd and Cooper Energy (MGP) Pty Ltd, the entities now trading under the Amplitude name.

ItemDetail
Ownership (VIC/L37)Amplitude Energy 50% (operator) / O.G. Energy 50%
Development conceptSubsea wells, flowlines and manifolds tied into existing CHN pipeline and Athena Gas Plant
Water depth / distanceWells roughly 9 km offshore, 55–80 m water depth
Annie resource65 PJ gross 2C (~32.4 PJ net to Amplitude)
Target productionUp to 90 TJ/d gross from 2028
Development costA$190–210m net to Amplitude, FY27–FY28
Production licenceVIC/L37 granted, announced 7 May 2026

The economics rest on reuse. Amplitude's own framing is that ECSP develops subsea reserves to replace existing Otway wells as they decline, using infrastructure already in place. That is a materially lower capital intensity than a greenfield offshore development, and it is the core of the investment case.

The well sequence and the FID package

Annie-2 reached total depth of 2,253 m measured depth on 28 October 2026 and was cleaned up over 9–10 November, then suspended. The FID announcement also confirmed the Nestor exploration well had been sanctioned (VIC/P76, with potential supply "as early as 2028" subject to success and approval) and that Juliet-1 had been completed and suspended ready for development.

The FID scope, as reported, extends beyond the wells to include subsea installations, pipeline re-lifing, control-system upgrades and modifications at the Athena Gas Plant — a reminder that brownfield tie-backs carry onshore scope as well as subsea scope.

A parallel corporate move has widened the resource base. In May 2026 Amplitude agreed to acquire a 50% interest in the discovered Artisan resource (VIC/L35) from Beach Energy for A$58.3m net upfront cash plus a future production royalty, with O.G. Energy taking 10% (Beach sold its 60% operated interest for A$70m headline). Amplitude now describes the ECSP development phase as underpinned by Annie, Juliet and Artisan.

Procurement: what is locked in and what is not

The visible award is subsea control umbilicals. JDR Cable Systems (TFKable Group) was contracted on 30 April 2026 for approximately 18 km of thermoplastic electro-hydraulic production control umbilicals, plus an option for about 13 km contingent on drilling success, with manufacture at Hartlepool and installation scheduled for late 2027.

The wider subsea package — flowlines, manifolds, subsea production systems, installation and wells connection — is where the commercial picture is less clear. Amplitude said at FID that "subsea contracting outcomes" were in line with internal expectations, which implies contracts were being settled around the decision. NOPSEMA's activity register still showed the "ECSP: Installation and Wells Connection" activity as pending titleholder notification at the time of review, which is consistent with offshore installation execution still being ahead rather than complete.

On steel specifically: the line pipe and bulk steel for flowlines and the CHN tie-in have not been visibly awarded in public sources. Given that flowline and installation contracting appears to be settling around FID, any remaining line-pipe requirement should be treated as possibly open but not evidenced — not as a confirmed opportunity. The one clearly closed package is the umbilical supply, and even that carries a drilling-contingent option rather than a fresh tender.

What to watch

  1. Installation contractor disclosure. The identity of the flowline/manifold installation contractor and the wells-connection scope is the single most informative missing data point. It will also clarify the residual steel requirement.
  2. Nestor result. A success adds a fourth well and triggers the umbilical option; a dry hole leaves the development on three fields.
  3. Updated resource estimates. Annie's 2C figure (65 PJ gross) predates the Annie-2 result. A revised estimate would test whether the reservoir upside is real or merely encouraging.
  4. Schedule discipline. First gas in 2028 requires installation in late 2027 and onshore Athena modifications in parallel. Any slip in the subsea campaign pushes directly into the 2028 target.

Why it matters beyond the Otway

ECSP is a case study in the economics now dominating mature Australian offshore gas: incremental barrels through existing infrastructure, 50/50 partnering to share capital, and a domestic east-coast market short enough to absorb the volumes. At up to 90 TJ/d gross it is not a mega-project, but it is the kind of incremental supply that substitutes for declining Bass Strait and Otway production.

For the supply chain, the signal is narrower than the headline. This is a subsea and onshore-modification project, not a fabrication-heavy one; the steel exposure is flowline and tie-in pipe plus Athena plant works, much of which appears to be contracting around FID rather than openly tendered. Suppliers should watch the installation award, not the well results, for the next actionable step.