CNI23's announcement that the first of two steam generators was hoisted into Lufeng unit 1's reactor building on 11 November is, on its own, an ordinary construction milestone. Its real value is as a scheduling marker: with the reactor pressure vessel placed on 10 July, the plant's primary circuit is now converging on the main coolant piping, the workscope that actually determines when a CAP1000 unit can be hydro-tested and fuelled.
What was installed
| Parameter | Value |
|---|---|
| Unit | Lufeng 1, CAP1000 (~1,250 MWe class), eastern Guangdong |
| Equipment | First of two steam generators |
| Placed | 11 November 2026 |
| Diameter / length / net weight | ~6 m / ~24 m / ~630 t |
| Prior nuclear-island milestones | CA03 module 23 Jan; RPV 10 July; main pipe welding and pressuriser reported Sept–Oct |
| Commercial operation target | 2030 (units 1 and 2) |
The two SGs together represent roughly 1,260 t of shop-fabricated pressure-boundary equipment per unit, before supports and insulation — among the largest single items fabricated for a PWR and, in the AP1000/CAP1000 architecture, the components that carry the design's distinctive two-loop, high-capacity layout.
Why this node matters more than it looks
The published significance — "laying a solid foundation for subsequent welding of the main pipeline assembly" — is the technically correct framing. On a two-loop AP1000-family plant, the SG outlet nozzles are the mating faces for the hot-leg transition; you cannot fit up and weld the primary loop until both SGs are set and aligned to the RPV. Chinese project reporting notes that the lift required on-site rotation and positioning in severely restricted space inside the nuclear island, with digital modelling and 3D collision checks used to keep placement within design tolerance. The second SG is now the critical item on that path.
From a fabrication standpoint the SG is the metallurgically demanding half of the nuclear island. The tube bundle — historically thermally treated Alloy 690 (Ni-Cr-Fe) tubing, tens of thousands of tubes and, as WNN notes, thousands of kilometres of tube length per unit — is where corrosion resistance, residual stress control and tube-to-tubesheet expansion quality determine the plant's operating life. The shell, channel head and tubesheet are heavy-section low-alloy steel forgings and plate (typically SA-508/SA-533 grades), clad or buttered with stainless or nickel-base weld overlay. That combination is why SG fabrication is a long-lead, few-supplier activity worldwide and why the Chinese supply base for nuclear-grade nickel alloy tube has been a strategic priority for CGN and CNNC.
The awkward sequencing at Lufeng
Lufeng is unusual, and the anomaly is instructive. The site was approved by NDRC in 2014 as four CAP1000 units, but the first machines actually built were units 5 and 6 — Hualong One (HPR1000) units approved in April 2022, with first concrete in September 2022 and August 2023, and operation targeted for 2027 and 2028. Units 1 and 2, the CAP1000s, only received State Council approval in August 2024; first safety-related concrete followed on 24 February 2025 (unit 1) and December 2025 (unit 2). Units 3 and 4 remain unapproved.
So Lufeng is two construction programmes sharing one site, one workforce and one licensing interface — CGN refers to it as a "double third-generation" base. Units 5 and 6 should be generating by the time units 1 and 2 enter commissioning, which means the CAP1000 units will inherit an operating site rather than a greenfield one. That is generally a construction advantage (shared infrastructure, experienced local teams) but it also compresses the window in which Lufeng's CAP1000 supply chain has to deliver, since the Hualong One line will by then be competing for the same heavy-forging and tubing capacity.
Approximate timeline of nuclear-island work
| Date | Milestone |
|---|---|
| 23 Jan 2026 | CA03 structural module (228.2 t) placed |
| 10 Jul 2026 | RPV hoisted into place |
| Sept–Oct 2026 | Main coolant pipe welding and pressuriser placement reported (dates not fully verified in primary sources) |
| 11 Nov 2026 | First SG set |
| Next | Second SG; completion of primary loop welding; then hydro-test and commissioning sequence toward 2030 |
The gap between first concrete (February 2025) and first SG installation (November 2026) — roughly 21 months — is consistent with CAP1000 module-heavy construction practice, in which civil works and large structural modules (CA01/CA03/CA20) advance in parallel with equipment delivery rather than sequentially.
Reading the demand signal
For suppliers and analysts, the relevant number is not one 630-tonne lift but the pipeline behind it. Lufeng 1 and 2 are two CAP1000 units; units 3 and 4, if approved, would add two more; and the CAP1000 line across Chinese sites — alongside the larger Hualong One fleet — sets the medium-term call on heavy forgings, Alloy 690 tubing, and the specialised welding and NDE labour that constrains installation schedules far more than steel tonnage does. CGN's own figure of about 52 TWh/yr and roughly 16 Mt of standard coal avoided across all six Lufeng units is a useful scale reference, but the binding constraint on delivery will be qualified manufacturing capacity, not demand.
Facts on the installation, dimensions, dates and approval chronology are as reported by WNN and CNI23/CINIE. Dates for the pressuriser and first main-pipe weld come from secondary aggregators and should be treated as unconfirmed. Material specifications and the assessment of schedule and supply-chain implications are the author's analysis.
Source & methodology +
MetalMate separates original-source evidence from summary and analysis. Verify the original source before procurement, legal or engineering decisions.
- Article status
- Published · Version 1
- Source date
- Not supplied
- MetalMate publication
- 14 November 2026
- Verification
- Automated evidence checks; not human reviewed
First steam generator installed at Lufeng unit 1 — World Nuclear News