Severstal's announcement that it has begun drying the refractory lining of the indurating machine at its new Cherepovets pellet complex reads like a housekeeping item. It is not trivial, though its significance is different from what the wording suggests. Refractory dry-out is the last purely mechanical step before an indurating machine can be heated to operating temperature: moisture must be driven out of the new lining slowly and on a controlled curve, because rapid steam generation inside a green refractory body causes spalling and cracking that would only surface later, during hot operation, as costly downtime on an asset that sits at the centre of a 10 million tonne per year flowsheet.
What the milestone actually signals
In process terms, the sequence from here is well defined: dry-out, then comprehensive testing of the integrated line, then hot trials with iron ore feed, then first product. Severstal CEO Alexander Shevelev has confirmed commissioning remains on schedule for autumn 2026, and parallel work continues on pelletizers, ball and vertical mills, electrical equipment and support infrastructure.
The credible reading is that the project has passed from construction risk into commissioning risk. That distinction matters to anyone tracking the project: the failure modes from here are technical (burner control, grate uniformity, pellet quality consistency) rather than logistical. The published execution record is unusually granular for a Russian project of this size:
| Date | Milestone |
|---|---|
| Late 2024 | Construction of roasting, pelletizing and grinding buildings begins |
| Aug 2025 | Installation starts on three 6.7 m × >13 m dry-grinding ball mills |
| End-2025 | Cold commissioning of indurating machine No. 1 |
| End-March 2026 | Cold commissioning of pelletizers and desulphurisation unit |
| Mid-Sept 2026 | Power supply energised to the complex |
| 26 Oct 2026 | Refractory lining drying begins |
| Autumn 2026 (target) | Hot trials and commissioning |
One caveat on the timeline: some secondary coverage has described "launch of pellet production" in September 2026. That refers to commissioning steps, not output. First pellets should be expected after hot trials, i.e. late 2026 at the earliest.
Why a pellet plant replaces sinter and coke batteries
This is where the project deserves more attention than a single headline. At full capacity the complex will lift pellets from roughly 50% to around 90% of the CherMK blast furnace burden, cutting the coke rate by about 25% and raising blast furnace productivity by about 9% (company figures reported by Russian industry media). Those are large numbers for an integrated works, and they come from well-understood metallurgy: pellets are uniform, low in fines and highly reducible, so they improve gas permeability and reduce the fuel needed per tonne of hot metal. Sinter, by contrast, requires coke breeze, returns fines and generates significant dust and sulphur emissions at the strand.
The consequence is a hot-metal cost structure that improves on three fronts at once — less coke per tonne, more tonnes per furnace, and no sintering plant to maintain, staff or permit. For an asset base facing high domestic coking coal and coke costs, that is a more reliable margin lever than anything available on the revenue side.
The emissions arithmetic is the part where careful readers should slow down.
| Environmental metric | Earlier figure (2023–24) | Current figure |
|---|---|---|
| Pollutant emissions reduction | 133,000 t/yr | 96,000 t/yr |
| GHG emissions reduction | — | 2 million t/yr |
| Facilities retired | 7 sintering machines, 2 coke batteries | 4 sintering machines, 2 coke batteries |
Analysis: the drop from 133,000 t to 96,000 t is most plausibly explained by the fact that three sintering machines were already idled in 2024 under the federal Clean Air (Чистый воздух) programme. The 96,000 t figure therefore represents the incremental benefit of retiring the remaining four machines and two coke oven batteries, not a downgrade of the project's environmental case. Readers comparing figures across years should check the baseline before drawing conclusions. Severstal has said the remaining sintering capacity will be shut down no later than early 2027, immediately after launch. The company puts environmental solutions investment at over RUB 7 billion, including wet desulphurisation with 99% gas purification.
The ore supply question is the real strategic pivot
The feedstock arrangement is underreported and arguably more consequential than the emissions story. The complex will be fed with iron ore from Severstal's Yakovlevskoye GOK and concentrate from Olenegorsk GOK — both captive units — ending purchases of third-party iron ore.
That closes a loop that was forced open after 2022, when access to Ukrainian Krivoy Rog concentrate effectively disappeared. Converting captive ore into high-grade pellets rather than buying sinter feed on the market reduces exposure to both logistics and price. It is also a hedge against the pellet market itself, where seaborne premiums have been volatile: a captive 10 Mt supply removes Severstal from that market as a buyer entirely.
Capex, timing and the counter-cyclical bet
The project has been officially costed at RUB 116 billion (about US$1.44 billion), up from the RUB 97 billion cited at announcement in 2023 — a roughly 20% increase that is unremarkable for a multi-year build of this complexity, but worth noting because Russian construction and equipment costs have inflated sharply over the period. About RUB 20 billion of equipment and materials was sourced domestically, with 47 suppliers from the Vologda region; 42,000 t of steel structures came from Severstal's own steel structures unit.
The timing is counter-cyclical. Russian domestic steel demand has been soft amid a construction slowdown, and Severstal passed on Q3 2026 dividends despite higher profit. Committing this sum to a captive raw materials project rather than to capacity expansion signals a clear priority: defend the cost position first, compete on volume later. When demand recovers, the 9% blast furnace productivity gain arrives as essentially free incremental hot metal capacity.
What to watch
- Hot trial outcomes and pellet quality. The three 6.7 m ball mills are among the largest installed anywhere; grinding circuit stability will determine whether the plant reaches nameplate quickly or ramps slowly.
- The sintering shutdown date. The "no later than early 2027" commitment is the trigger for the emissions benefit and the maintenance-cost saving; slippage there delays the economics, not just the environmental headline.
- Whether the 2027 coke rate is delivered at CherMK. A 25% reduction is a strong claim; it depends on burden configuration and blast furnace practice as much as on pellet quality.
- Downstream and upstream equipment suppliers. The main process equipment has been reported as Chinese-supplied, but the technology vendor for the indurating machine has not been publicly confirmed in the sources reviewed. Refractory supply and the dry-out contractor are similarly undisclosed.
The refractory dry-out is a technicality. The fact that Severstal is now performing it on schedule is not.
Source & methodology +
MetalMate separates original-source evidence from summary and analysis. Verify the original source before procurement, legal or engineering decisions.
- Article status
- Published · Version 1
- Source date
- 27 October 2026
- MetalMate publication
- 27 October 2026
- Verification
- Automated evidence checks; not human reviewed
Severstal targets 2026 launch for Cherepovets pellet plant — SteelOrbis