SSE's half-year results, published on 18 November, contained little of the theatrical. Around 150 turbines installed across the three phases of Dogger Bank, roughly 100 of them commissioned, 52 of 95 in place at phase B, foundations and array cables complete at phase C. The signal was buried in the phase-A caveat: additional work is required on some turbines installed during the first campaign to bring them to the "required quality and reliability standards", with remediation under way offshore.

The consequence is a schedule that has quietly moved. Dogger Bank A's 1.2 GW is now expected to be substantially available by the end of Q1 2027, with remaining capacity online through final commissioning by end-Q3 2027. Earlier market notices had pointed to substantial availability by end-2026. That is roughly a one-quarter slip on a project whose first power flowed in October 2023.

What the numbers actually tell us

The headline 150/100 split is more revealing than it looks once broken down by phase.

PhaseCapacityTurbinesInstalled (18 Nov 2026)Status
Dogger Bank A1.2 GW95 (implied)~98 by residual (est.)Installation complete or near-complete; commissioning and remediation
Dogger Bank B1.2 GW9552Installation ahead of phase A's rate; most capacity available H1 2027
Dogger Bank C1.2 GW870Foundations complete, array cables complete; testing and commissioning
Total3.6 GW277 (est.)~150

Turbine counts: B and C are stated (95 and 87 respectively); A is derived by subtracting B's 52 from the ~150 total — an analyst estimate, not an SSE figure. 277 is the resulting whole-project total.

Two things follow. First, phase A is effectively built out. The bottleneck there is no longer vessels or foundations but the condition of machines already standing in the water. Second, the phase C figure indicates that foundations and cables — the steel-heavy, schedule-critical package — are done well ahead of the turbine campaign, which Cdeler will begin in Q3 2027 when its newbuild Wind Apex joins Seaway's Ventus. In other words, Dogger Bank C's critical path runs through turbine supply and vessel availability, not through monopiles or subsea cable.

The phase-A problem is a reliability problem, not a construction one

SSE's language — "required quality and reliability standards" — is deliberately non-specific, and it matters that the company has not quantified it publicly. Trade reporting suggests the affected population is in the dozens of machines rather than the majority, which is consistent with SSE's statement that most phase-A turbines have been commissioned. The affected equipment is widely understood to be GE Vernova Haliade-X hardware, and the remediation follows the August 2024 blade event at phase A, which SSE Renewables confirmed at the time involved an installed GE Vernova machine and triggered a root-cause investigation.

The distinction between "repair" and "major component exchange" is the commercially important one. A blade swap is a heavy-lift operation requiring a jack-up or a specialist blade vessel, a weather window and a crane spread — expensive, serialised and slow. A gearbox or generator exchange is worse. Each returns a machine to the installation queue rather than the commissioning queue, which is precisely why final availability slipped a quarter even though the installation phase is essentially finished.

For suppliers, this is the awkward second act of the drive to larger rotors and higher ratings. The Haliade-X entered the market at a scale where the industry's field data on drivetrain and blade loads was thin. Dogger Bank A — the first commercial deployment of the platform at volume — is functioning as that field data, at the developer's expense and on the developer's schedule.

Why phase B is the real test

SSE's statement that phase-B installation is "significantly ahead" of phase A's initial campaign is the most consequential operational claim in the release, and it deserves scrutiny rather than repetition. A faster installation rate matters only if the machines going in are not the machines coming back out.

There is a reasonable case that they are not. Dogger Bank B is installing later units of the same platform, after root-cause work on the blade event and, presumably, revised manufacturing and quality-control regimes. If that holds, phase B's H1 2027 availability target is credible and Dogger Bank's aggregate output ramps steeply through 2027 — phase A's 1.2 GW substantially available by end-Q1, phase B's 1.2 GW in H1, and phase C following from Q3.

If it does not hold, SSE faces a second remediation campaign on a phase already counted as ahead of plan, and the phase-C timetable becomes exposed in turn. That is the single largest execution risk in SSE's renewables portfolio, and the market will be watching the phase-B commissioning curve through the first half of 2027 for evidence either way.

Berwick Bank B: a cheaper, later, lower-risk replica

The Scottish project, at 1.4 GW, offers the instructive contrast. Final investment decision is now targeted for H2 2027 — late 2027 by SSE's own framing in related announcements — with preferred supplier agreements signed across the scope: Siemens Energy for turbines and offshore substations, Seaway7 for around 90 fixed-bottom foundations and inter-array cables, preparatory offshore construction potentially starting in 2028.

Three differences from Dogger Bank are worth naming. First, the turbine supplier changes: Siemens Energy rather than GE Vernova, which diversifies SSE's technology exposure at exactly the moment Dogger Bank demonstrates why that matters. Second, around 60% of expected debt financing has been locked in at swap rates below 5%, a hedging position that materially de-risks the investment case in a way Dogger Bank's earlier financing could not. Third, the project is a near-copy of a design SSE has now built three times over, with foundation and cable contractors appointed before FID rather than after.

The scheduling is not accidental. An FID in late 2027 means Berwick Bank B's construction overlaps the final commissioning of Dogger Bank C — a deliberate sequencing that keeps SSE's offshore construction organisation and its vessel slots continuously employed rather than demobilising and remobilising.

What to watch

The relevant question for the supply chain is not whether Dogger Bank reaches 3.6 GW — it will — but what the phase-A experience does to procurement behaviour. Three markers over the next twelve months:

  • Phase-B commissioning data. Turbines installed versus turbines exporting power at phase B through H1 2027 is the cleanest available test of whether the Haliade-X quality issue was a phase-A cohort problem or a platform problem.
  • Remediation disclosure. Whether SSE quantifies the affected turbine count and the associated cost — at interim results or in the full-year statement — will indicate how confident the company is that the issue is closed.
  • Berwick Bank B contract awards. Preferred supplier status becomes firm contract award only at FID. The gap between the two is where Siemens Energy's blade production at Hull, Seaway7's installation fleet commitments and the 60% hedged debt all either hold or unwind.

For steel and fabrication suppliers, the Dogger Bank story is largely concluded: monopiles, transition pieces and array cable are in the water or on the quayside at all three phases. The live demand signal is Berwick Bank B's roughly 90 foundations and its substation platforms, ordered against an FID more than a year away and a construction start in 2028. That is a slower, better-hedged pipeline than the one that built Dogger Bank — and, given what phase A has taught the industry about scaling machines faster than field data accumulates, a more prudent one.


Reporting basis: installed and commissioned figures, phase-B counts, phase-C status and the revised phase-A schedule are as reported by OffshoreWIND.biz from SSE's 18 November interim results. The phase-A turbine count, the 277-unit total and all forward-looking judgements are the author's estimates and analysis. The affected-turbine population ("dozens") is drawn from trade reporting and has not been quantified by SSE in the material reviewed.

Source & methodology +

MetalMate separates original-source evidence from summary and analysis. Verify the original source before procurement, legal or engineering decisions.

Article status
Published · Version 1
Source date
20 November 2026
MetalMate publication
20 November 2026
Verification
Automated evidence checks; not human reviewed

Around 150 Turbines Installed at 3.6 GW Dogger Bank Wind Farm, Remediation Work Underway at Dogger Bank A — OffshoreWIND.biz