Rashtriya Ispat Nigam Limited (RINL) confirmed on 27 October that its Visakhapatnam Steel Plant (VSP) is once again rolling TMT rebar. The physical restart actually came in mid-October, according to Indian media reports a day before the SteelOrbis confirmation, ending a stoppage that began in June 2026. The proximate cause was not a shortage of crude steel but "extensive repair work at its coke oven batteries."
That distinction is the whole story. A coke-oven outage manifesting as a rolling stoppage tells you where RINL's binding constraint sits, and what the mill's path back to viability actually depends on.
Why a coke oven stops a rebar mill
Coke oven gas (COG) is a steel plant's principal in-house gaseous fuel. At an integrated long-products works like VSP, the reheating furnaces that feed the rolling mills — the bar and structural mills that produce TMT — run on coke oven gas or a mixed gas blend. When batteries are taken out for refractory repairs, COG availability falls, and rolling mills become fuel-constrained even with ample billet inventory.
The sequence at RINL fits this pattern precisely. Third-party reporting in 2026 indicated that Coke Oven Batteries 1 and 2 were largely non-operational and Battery 5 was running at reduced capacity, contributing to plant-wide gas shortages; Indian Oil was reportedly lined up to supply piped natural gas as a stopgap. The Ministry of Steel's 2025-26 Annual Report is described as recording that Battery 5's mixed-gas under-firing system was commissioned in December 2025 specifically to free additional COG for rolling-mill furnaces — a direct, if partial, fix for exactly this bottleneck.
The corollary: RINL's rebar output remains hostage to coke-oven reliability. RINL has a 2026 tender outstanding for "revival of down ovens" in its coke oven batteries, valued at roughly ₹154 crore with a 730-day work period, plus separate tenders for refractory and mechanical upkeep of Battery 3. This is a multi-year rehabilitation programme, not a completed repair. Further rebar rolling interruptions cannot be ruled out.
Rebar is the commercial core, not a peripheral product
For a long-products producer, TMT is where margin and brand live. RINL sells "Vizag TMT" in Fe-500D and corrosion-resistant (CRS) grades across 8–32 mm, with larger sizes up to 40 mm for infrastructure; market estimates put bar output from the structural and merchant mills at roughly 3,000–4,000 t/day depending on the product mix — an estimate, not an RINL disclosure. RINL's own reporting shows that rebar, rounds and wire rod coil together accounted for 72% of sales in FY2022-23, up from 56% two years earlier, and that project customers take roughly a quarter of volumes.
Four months out of this product is therefore a materially worse outcome than four months of weak semis sales. A large share of semi-finished and pig iron in the mix, which ICRA flagged in its rating rationale, is a symptom of a mill that has been unable to convert its liquid steel into higher-value finished long products. Every month a rolling mill idles, the product mix degrades toward semis and the net sales realisation falls.
The financial context: a fragile, partly policy-manufactured recovery
The restart matters because RINL's turnaround, such as it is, has been built on operating rates rather than structural reform:
| Metric | Figure | Period |
|---|---|---|
| Liquid steel capacity, VSP | 7.3 Mtpa | Current |
| Hot metal output | 3.913 Mt | FY2024-25 |
| Saleable steel | 3.459 Mt | FY2024-25 |
| Comprehensive loss | ₹1,607 crore | FY2024-25 |
| Net worth | ₹1,137 crore (positive) | 31 Mar 2025 (vs −₹4,538 crore at 31 Mar 2024) |
| Capacity utilisation | 94% (19,401 t/day hot metal); ₹54 crore monthly profit | January 2026 |
| Revival package | ₹11,440 crore (₹10,300 crore equity + ₹1,140 crore debt-to-preference conversion) | Approved Jan 2025 |
The swing from a deeply negative to a positive net worth is largely the arithmetic of the government's equity infusion — ICRA noted that ₹10,644 crore of the ₹11,440 crore package had been received by November 2025. The January 2026 monthly profit was a genuine operating signal, but it came at 94% utilisation, an exceptional rate for a plant that had been running a single blast furnace at around 30% capacity. Holding near that level is the actual test; the Ministry of Steel's target of ~19,000 t/day hot metal (about 92.5%) leaves little headroom.
This is where the rebar restart connects to viability: high utilisation only converts into cash if the output is sold as finished long products into a firm construction market. Idle rolling capacity while blast furnaces run hard is the worst possible combination — you incur the full cost of ironmaking and capture only semis pricing.
What it means for the market
VSP's rebar volumes are small against India's total long-steel supply, so the restart is unlikely to move national rebar prices on its own. Its relevance is regional and relational: Vizag TMT is a recognised brand with a dealer network concentrated in southern and western India, and a four-month absence forces project buyers and dealers to re-contract with secondary producers. Recovering that shelf space — and the specification approvals that go with project supply — is slower than restarting a mill. RINL's claim that customers responded positively is a company statement, not evidence of recovered share; as SMM noted, the supply impact "will depend on sustained production and market dispatches."
Two things to watch over the next two quarters:
- Coke-oven availability. If restructuring of the older batteries advances and Battery 5's gas contribution holds, rebar rolling can run continuously. If not, expect further rolling curtailments that will be read in the market as demand weakness when they are in fact a fuel problem.
- Product mix and realisations. A sustained shift back toward finished long products, rather than semis and pig iron, is the cleanest available indicator that RINL's recovery has moved from policy-supported to operationally self-sustaining.
For buyers of long products in south and west India, the practical takeaway is that Vizag TMT availability has improved but that supply reliability remains contingent on a rehabilitation programme with a two-year horizon. For anyone tracking RINL as a credit or policy story, the lesson of 2026 is that the mill's headline constraint — cash, capital, government support — has been substantially addressed, while its physical constraint has not.
Note on dates: the restart occurred in mid-October 2026 according to Indian media reporting on 26 October; 27 October is the date of the company confirmation carried by SteelOrbis. Output and price figures attributed to market reporting are estimates, not company disclosures.
Source & methodology +
MetalMate separates original-source evidence from summary and analysis. Verify the original source before procurement, legal or engineering decisions.
- Article status
- Published · Version 1
- Source date
- 27 October 2026
- MetalMate publication
- 27 October 2026
- Verification
- Automated evidence checks; not human reviewed
